Under the approved code of practice for load lifting and rigging slings assembled with wire rope grips are not to be used for lifting.
To preform to manufacturers specifications the correct number of grips must be installed correctly and tightened to the correct torque using a torque wrench.
The correct way to install is shown below:
Tightening torque for the DIN1142 and FED SPEC FFC-450 are shown in the tables below:
Torque for DIN1142 are on lubricated threads, torgues for FED SPEC 450 are on dry threads |